|
To formalise the ICAAP and facilitate its review by the Banco de España, the capital assessment process should be included in a report known as the yearly internal capital adequacy assessment report (hereafter "the capital report"). This will be sent to the Banco de España along with the year-end own funds reporting and is therefore a confidential document.
The report should contain the following sections:
1. Executive summary.
2. Internal governance, risk management and internal audit of risks.
3. Measurement of risks and quantification of the capital needed to cover them.
4. Aggregation of the capital needs and reconciliation adjustments.
5. Capital planning.
6. Programme of future measures.
7. Other matters.
Given the importance this report will have for the institution itself and for the Banco de España review, the institution's management (Board of Directors or equivalent body) should be apprised of the report's content and approve it.
Detailed below are the contents of the different sections of the report. The institutions should, however, adapt the content of the capital report to their own needs and circumstances, as this report should contain the relevant information substantiating the summary, conclusions and programme of future measures. The principle of proportionality to be applied in the internal capital adequacy assessment process should also be reflected in the content of the report, so that it is focused on the relevant risks and aspects for the institution.
The capital report should be self-explanatory. However, to prevent institutions from duplicating information published previously on their own initiative or in compliance with legislation, the various sections of the report, except Section 1 (executive summary and conclusions) and Section 6 (programme of future measures), may be completed through the inclusion of parts of other previously published reports, indicating the source. Such sections should be updated and attached as annexes. In any event, the information included should conform to the aim and requirements of the capital report.
Given the foreseeable stability over time of the systems and procedures relating to internal governance, risk management and internal audit of risks, the sub-sections of Part 3,2 of the report may be completed by reference to the sub-sections of the report submitted in the previous two years, as long as significant changes have not taken place. Nevertheless all the sections relating to internal capital adequacy assessment should be updated every year and a general update of Section 3.2 of the report carried out every three years.
Annex 1 includes a report format which concludes with the summary ICAAP return. In case of groups of credit institutions the summary return should be broken down by significant institution. To this end significant institutions will be identified in Section 1 of the capital report. This identification will, when appropriate, be carried out in co-operation with other supervisors. The different sections or sub-sections of the report should also be broken down by significant institution when there are major differences with respect to the group.
3.1 Executive summary and conclusions.
The aim of this section of the report is to offer an overview of the internal capital adequacy assessment process and of the main conclusions, which are set out in greater depth in the other sections of the capital report.
First, the scope of application of the ICAAP should be indicated (individual institution, consolidated or sub-consolidated group) and, if a consolidated group of credit institutions is involved, the institutions included in the ICAAP should be listed in an annex, showing those considered significant for the purpose of the last paragraph of section 3. According to that paragraph, if in a group of credit institutions there are significant differences in any relevant subsidiary credit institution with respect to the group as a whole, such differences should be specified in the related section of the capital report, indicating the institution where such differences are present and, where appropriate, the envisaged period within which the subsidiary institution in question will come under the general managerial scope of the group.
Since the capital report contains sections relating to different departments of the institutions, the department or person responsible for the integration of the different parts and for their review should be indicated. The capital report will indicate the contact person with the Banco de España on matters relating to the capital report[6]. The capital report should be signed by the individual designated as the contact person for the Banco de España. The date of its approval by the Board of Directors or equivalent body should be indicated.
Next, this section should reflect the following:
3.1.1 Risk profile of the institution[7]
The material risks to which the institution is exposed should be outlined, and a summary assessment of the exposure to the risks and of the quality of these exposures should be made. The assessment should refer to the inherent risk and draw on quantitative data wherever possible. In this connection, exposure and risk quality indices and parameters suited to the different risks should be used. The section should conclude with an analysis and assessment of the institution's overall risk profile.
When presenting the inherent risk in the capital report, institutions should follow the risk structure and definitions and the risk matrix ratings (high, medium-high, medium-low or low) used by the Banco de España in its supervisory process. This matrix is published in the document “The Banco de España Supervisory Model”. To establish the rating for each risk, institutions should follow their internal criteria.
This section of the report shall finish with an analysis and assessment of the institution’s overall risk profile.
3.1.2 Governance and risk management and control systems
A broad assessment should be made of the suitability of internal governance and of risk management and control systems for the institution's risk profile. Where necessary, weaknesses should be highlighted, indicating whether they are in the process of being resolved or not.
3.1.3 Own funds target: level, composition and distribution among legally independent group institutions[7]
The own funds target should be established in terms of core capital and as a capital ratio (e.g. 7%). This target should be compared with the core capital actually available on the capital reporting date. To this end, the definition of core capital used will be that of “common equity” established by the Basel Committee, including any criteria for applying this definition set out in European and Spanish legislation.
In addition, groups of credit institutions should indicate their policies and targets for the distribution of capital among the various significant legally independent institutions, considering the individual risks at each one, and specifically indicating the policy and own funds target of the group parent. To do this, the ability or actual possibility to transfer, if necessary, capital among the different group institutions by means of dividends or capital increases should be taken into account. The aforementioned targets should be compared with the own funds effectively available at each credit institution (parent or subsidiary) at the reporting date, stating any available own funds in excess of the limits.
On setting own funds targets, it should be indicated whether the rating the institution wishes to maintain has been taken into account and if so, what that rating is.
3.1.4 Capital planning
Capital planning for the future should be summarised and assessed, including the institution’s policy for dividends (where appropriate) and capitalisation, and indicating the time period (necessarily the medium-term) the planning spans.
3.1.5 Programme of future measures
Where appropriate, the significant limitations or weaknesses identified in the ICAAP, the measures envisaged in the plan of action to correct them and also the possible changes (improvements) foreseen in risk management should be summarised.
3.1.6 Other matters
Other matters that the institution considers relevant should be reflected.
3.2 Internal governance, risk management and internal audit of risks.
This section of the report includes the qualitative aspects of the ICAAP relating to internal governance, risk management and the internal audit of risks. The content of this section should be proportional to the size and complexity of each credit institution. For groups of credit institutions the different sub-sections should be broken down into significant subsidiaries when there are major differences with respect to the group.
3.2.1 Internal governance
The aim of this section is to summarise the institution's organisation and governance policies in respect of risk management.
In preparing this section, regard should be had to the principle of proportionality that should underlie all information included in the capital report.
This section of the report should specifically include:
3.2.1.1 Description of the institution’s organisation
The institution’s organisation chart should be indicated, including the Board of Directors or equivalent body and its committees, with their composition, functions and responsibilities, organisational and working rules, powers and delegations. Diagrams reflecting the organisation and functional reporting lines of the related bodies should be included in this section.
3.2.1.2 Functions and responsibilities of the Board of Directors relating to the management of risks, their internal control and capital adequacy
It should be specified how the institution's Board of Directors takes responsibility for:
- The nature and level of the risks borne.
- The correspondence between this level of risks and existing capital.
It should be stated how the institution's Board of Directors establishes the corporate risk culture and ensures that:
- The sophistication of risk management and measurement processes is suited to the institution’s risks and business.
- The internal control systems are appropriate for ensuring orderly and prudent management of the institution's business and risks.
- The own funds targets are tailored to the institution’s risk profile and to the economic environment in which it operates.
For illustrative purposes, this section should include a summary report of the risk-related activities performed by the Board of Directors during the year.
3.2.1.3 Internal governance assessment
This section should conclude with a broad assessment of the institution's internal governance relating to risk management, indicating where appropriate deficient aspects.
The assessment process will consider, among other things, the degree of compliance with the provisions of the EBA Guidelines on internal governance (GL44) regarding the different aspects of it, as shown in Annex 4. Besides evaluating this compliance, weaknesses or vulnerabilities observed should be made apparent, considering, following, where appropriate, the principle of proportionality set out in those guidelines. [8]
When making this valuation it should also be considered the degree of fulfilment of the recommendations of the “Unified Code of Good Governance” approved as “unique document with the recommendations of corporate governance” by the CNMV on 22 May 2006.
The conclusions of the assessment process will be shown in this section of the report. [8]
3.2.2 Risk management
This section of the report should address the following:
3.2.2.1 Corporate risk culture: general principles of risk management
The general principles of risk management should be summarised, indicating the governing body that establishes these principles and the internal policies for their application. It should also be indicated how these internal policies are communicated to the different organisational levels.
The functions and responsibilities of the area of overall risk management and control should be summarised, and it should be indicated how this area integrates into the organisation chart and into the risk function.[8]
3.2.2.2 Specific aspects of each risk
For each of the risks of significance to the institution, the following aspects should be indicated:
3.2.2.2.1 Risk policy: limits, diversification and mitigation.
The maximum exposure limits set for each risk and the policies in place for their diversification and mitigation should be stated. It should be indicated how these policies are applied in practice in the institution's decision-making process.
3.2.2.2.2 Organisation of the risk function and of powers, responsibilities and delegations. Risk control function. Reports on the risk function.
The hierarchy established in the institution for the management of each risk (in its three facets: assumption, measurement and control) and the delegation of functions and responsibilities should be described. The levels of management centralisation-decentralisation, the boundaries of responsibility and authorisation, and the separation of the functions of the various risk management bodies should be explained.
If, for some risk there exists a separate or independent risk function, the structure and responsibilities of the attendant control function should be indicated.
3.2.2.2.3 Management tools: measurement, admission, communication, control and monitoring systems.
A summary description should be given of the tools and procedures for the management of the various risks, indicating the measurement or risk assessment methodology, the approval, communication, control and monitoring systems and procedures, and the IT systems supporting management, including the stress tests carried out[7] and, where appropriate, the historical databases used for measurement.
The periodic or sporadic management reports used and their recipients should be stated, identifying specifically those addressed to the board of directors.
3.2.2.2.4 Policy and tools for the monitoring and recovery of impaired assets.
For those risks in which it is appropriate, the systems and procedures for the monitoring and recovery of impaired assets and bad debts should be indicated.
3.2.2.2.5 Risk management assessment.
The policy, organisation (suitability of the organisational structure, of the delegation of functions, of the activity of the risk-related committees), measurement methodology and management and control systems and procedures of each risk should be assessed.
3.2.2.3 Overall assessment of risk management
Based on individual assessment of the management and materiality of each risk for the institution, a general assessment should be made of the policy, organisation (suitability of the organisational structure, of the delegation of functions, of the activity of the risk-related committees, etc.), measurement methodologies, and risk management and control systems and procedures.
3.2.3 Internal audit of risks
The organisation and reporting lines of the internal audit function should be described. Further, the report should address the following in this section:
3.2.3.1 Risk review-related internal audit tasks
The functions assigned and the resources allocated to periodical risk review by internal audit should be indicated.
Where appropriate, details should be given of the matters examined by internal audit in the area of risks. By way of example, the following may be mentioned:
- Compliance with risk management internal rules (limits, procedures).
- Effective and appropriate use of risk management tools by the organisation as a whole (use test).
- Review of the internal control functions of the risk function, and of their appropriateness and effective functioning.
- Suitability of risk management IT systems.
- Precision and sufficiency of the data used.
- Assessment of risk measurement methodologies.
The main conclusions from the internal audit reports derived from the audit work conducted in relation to the various risks and the corrective measures proposed, if any, should be reflected, indicating the governing body to which the reports are addressed.
3.2.3.2 Internal audit assessment
This section should conclude with an assessment of the suitability of the internal audit function and resources in respect of the tasks assigned to it in the area of risks.
3.3 Measurement of risks and quantification of the capital needed to cover them
This section in the report and the following Section 3.4 include the quantitative aspects of the ICAAP, i.e. those relating to the identification and individual quantification of the different risks to which the institution is exposed and their subsequent aggregation.
The capital calculated in these two sections should be considered in the capital planning in Section 3.5, and should finally be used to determine the own funds target established in Section 2.1, since the institution should, in the present and also in the future period covered by its capital plan, hold a level of capital tailored to its risks and an appropriate buffer in excess of its minimum capital requirements under Pillar 1.
For the assessment of Pillar 1 risks in the ICAAP (i.e. credit, market and operational risks), institutions should, in each of the risk categories indistinctly, choose one of the following options:
- Option 1: use the approach and result obtained under Pillar 1, including where necessary the aspects of each risk not considered in this pillar. Here, institutions should only explain the differences between the calculations of the ICAAP and those of Pillar 1, which should be those due to the additional aspects included.
- Option 2: adapt the Pillar 1 approach to the institution’s risk management. If institutions use this option, they should justify this adaptation which, moreover, should be used in the management of the related risk (without prejudice to the Pillar 1 use test). They should also explain the differences between the results of the ICAAP for this risk and those of Pillar 1. The more the adaptation and the result diverge from the treatment under Pillar 1, the more exhaustive the justification and explanation should be.
For the remaining risks to be taken into account in the ICAAP, the institutions should make their own estimates which they should include in the related section of this report. To facilitate these estimates for the overall group of institutions supervised by the Banco de España, a simplified option is included for each risk aimed, in general, at institutions that apply standardised approaches under Pillar 1. When simplified options are thus indicated, they may also be used by institutions that apply advanced approaches under Pillar 1. Reasons justifying the use of these simplified options need not be given. The institutions that use simplified options may also use own estimates if they consider them more appropriate, but in that case they should give the reasons why they did so and use the related measurement methodology in the management of the risk involved.
In the case of groups of credit institutions, if for some risk there are significant methodological differences of measurement in some major institution, these differences should be included in the corresponding sub-section.
This section of the report should include:
3.3.1 Assessment of capital needs for credit risk
To evaluate credit risk capital needs, institutions should use one of the following options:
- Option 1: use the methodology of Pillar 1 (standardised or IRB) and the result obtained therewith. They should aggregate to this the aspects of the credit risk not considered under Pillar 1, specifically the residual risks derived from the use of risk mitigation techniques (e.g. ineffective guarantees or collateral derived from deficient implementation or management thereof, etc.) and the possible heightened risks stemming from asset securitisation and from lending denominated in foreign currency (e.g. the possible negative effects on the capacity to pay of borrowers as a consequence of fluctuations in interest and exchange rates. [8]
Institutions may replace the foregoing aggregation with an analysis of ther following that justifies why additional capital is not needed[8]:
- Effectiveness of mitigation techniques used in the capital calculation under Pillar 1. Indeed, irrespective of the Pillar 1 methodology used (standardised or IRB), Basel II stimulates and recognises the use of different credit risk mitigation techniques by reducing the capital requirements. Therefore it is necessary that the institutions evaluate the effectiveness of these mitigation techniques, which in many cases require an active and complex management.
- The significant and effective transfer of exchange rate risk from customers in foreign currency lending. [8]
- The significant and effective transfer of risk to third persons and the non-existence of implicit support in the different securitisation programmes undertaken by the credit institution.
- Option 2: adapt the Pillar 1 approach to the institution’s credit risk management. If this option is used, institutions should justify this adaptation. The more the adaptation and the result diverge from the treatment in Pillar 1, the more exhaustive the justification should be. This adaptation should be used in credit risk management. Further, the differences between the results thus calculated and those obtained in Pillar 1 should be explained.
By way of example, two possible situations are mentioned:
- Use of the standardised approach under Pillar 1 and use of the IRB approach for certain portfolios under Pillar 2, since there is a rating system in place for the management of such portfolios.
- At institutions that apply IRB approaches under Pillar 1, the use of correlations other than those used in Pillar 1 in specific portfolios, since they adapt better to the actual risk situation at the institution and are effectively being used in the management of such portfolios; consideration of the benefit of geographical diversification between countries in a different economic area (e.g. between Europe and Latin America), for the same reason. In this case it may be necessary to reconsider the correlations used for the borrowers within each portfolio since when loan portfolios are disaggregated to consider the benefit of the diversification among them, borrowers within each sub-portfolio will show a more uniform behaviour and therefore a higher correlation.
In both options, institutions should separately include in this section their assessment of capital to cover the risk of equity securities not held for trading. To do this they may use the Pillar 1 approach or another methodology they consider more appropriate for managing this risk. If these equity portfolios are significant, institutions should use methodologies sensitive to the real risk assumed. Credit institutions that use methodologies other than those of Pillar 1 should reconcile, if necessary, the results of these methodologies to those obtained from a solvency analysis, in accordance with Section 3.4.2.
The capital report should reflect the option used, the result obtained and, moreover:
- For institutions that use option 1, a specific analysis of the risk mitigation techniques used and their potential residual risk, and of the asset securitisation programmes and of lending in foreign currency and its potential risk not envisaged in Pillar 1. Both risks should be quantified if they are significant.[8]
- For institutions that use option 2, a summary of the methodology used and the reasons for doing so, with the sufficient degree of portfolio disaggregation.
3.3.2 Assessment of capital needs for credit concentration risk
To assess capital needs for credit concentration risk, institutions should use one of the following options:
- Simplified option[7]
: Institutions should calculate the sectoral concentration index (SCI) of their credit portfolio using the method set out in Annex 2. If this index is greater than 12, their capital requirements for credit risk under Pillar 1 should be increased as follows:
Institutions should also calculate the individual concentration index (ICI) of the 1,000 borrowers with the largest direct risk exposures using the method set out in Annex 2. If the ICI exceeds 0.1, they should multiply the Pillar 1 credit risk capital requirements for the borrowers included in the index by the multiplier obtained by linear interpolation of the values in the following table:
Additionally, institutions should include a list of the 10 largest indirect and counterparty risks, indicating in both cases the obligor and the amount.
- General option: institutions should use the in-house methodologies they consider to be most suitable, which they should justify and use in managing this risk. This option is obligatory for institutions using IRB approaches under Pillar 1. Institutions must assess their individual (including counterparty and indirect risk), sectoral and geographical concentration. For the purpose of individual and sectoral concentration analysis, the institutions using this option should also calculate their capital needs according to the simplified option above.
It is possible for the measurement of capital needs for this risk to give a result of no capital need, but institutions must justify this outcome.
The capital report should set out the option used, the result obtained and, moreover:
- The information requested in Annex 2.
- The institutions using the general option should summarise the method used and set out the basis for it.
3.3.3 Assessment of capital needs for market risk
To assess capital needs for market risk, institutions should use one of the following options:
- Option 1: use the method and result obtained under Pillar 1 (standardised method or VaR models).
- Option 2: adapt the Pillar 1 approach to the institution’s market risk management. If this option is used, the institutions should justify this adaptation. The more the adaptation and result diverge from the Pillar 1 treatment, the more exhaustive the justification should be. The methodology used should be that employed in market risk management and the differences between the results thus calculated and those obtained in Pillar 1 should be explained.
By way of example, two possible situations are mentioned:
- The institutions using Pillar 1 standardised approaches to measure market risk may use VaR models totally or partially, provided they are actually used in managing market risk in the related portfolios.
- The institutions that use VaR models in Pillar 1 may adapt them in the ICAAP, using parameters actually employed in the management of this risk.
Institutions with no capital needs for this risk need not fill out this section.
In this section, institutions should assess separately the on-balance-sheet structural exchange risk if this risk is material. To do this, they should use methodologies suitable for the level of risk assumed which are effective in assessing the real risk.The capital report should include the option used, the result obtained and, moreover:
- For institutions using option 1, a specific analysis of the material aspects of this risk not captured in Pillar 1, and the additional capital needs, if any.
- For institutions using option 2, a summary of the methodology used and the reasons for doing so, at a sufficient level of detail.
3.3.4 Assessment of capital needs for operational risk
To assess capital needs for operational risk, institutions should use one of the following options:
- Option 1: use the methodology and result of Pillar 1 (basic indicator, standardised or AMA approaches).
- Option 2: adapt the Pillar 1 approach to the institution's operational risk management. In this case institutions should justify this adaptation. The more the adaptation and result diverge from the Pillar 1 treatment, the more exhaustive the adaptation should be. The methodology used should be that employed in operational risk management. The differences between the results thus calculated and those obtained in Pillar 1 should be explained.
By way of example, two possible situations are mentioned:
- An institution using the basic indicator approach under Pillar 1 could use the standardised approach in its ICAAP, for some or all of its lines of business.
- An institution using the standardised approach under Pillar 1 could use the AMA approach in its ICAAP.
The capital report should set out the option used, the result obtained and, moreover:
- For institutions using option 1, a specific analysis of the material aspects of this risk not captured in Pillar 1. A possible way to fulfil this requirement will be by means of a yearly internal audit report on the management, control and impact of this risk in the institution.
- For institutions using option 2, a summary of the methodology used and the reasons for doing so, at a sufficient level of detail.
3.3.5 Assessment of capital needs for interest rate risk in the banking book
To assess the capital needs for interest rate risk in the banking book, institutions should use one of the following options:
- Simplified option: institutions should use the adverse impact on their economic value referred to in Rule [4 of the capital assessment chapter] of Circular CBE 2008 on own funds, which is included in column 2 of Return RP51.
If this adverse impact reduces an institution’s economic value to below 130% of its total minimum capital requirements under Pillar 1, capital equal to 100% of the difference between 130% of that minimum capital requirements and the diminished economic value after the aforementioned adverse impact should be allocated. For this purpose the Banco de España may issue methodological guidelines for the treatment of sight deposits and publish the specific values of the impact on interest rates that are to be considered in the major currencies.
However, if the adverse impact calculated above reduces the initial economic value by less than 5% of its value, institutions may give reasons justifying why no capital is needed to cover this risk according to the above calculation, even though, after impact, the capital stands below the aforementioned 130% of Pillar 1 minimum capital requirements, provided that after impact it does not stand below 105% of those minimum capital requirements.
To this end, institutions should consider a maximum duration of 4 years for non remunerated sight deposits and deduct from them a minimum percentage of 10%. This minimum will be considered volatile and therefore have a duration of zero.[7]
In any case, the capital assigned for this risk by an institution should be at least the largest of:
a) The reduction in the economic value due to the adverse impact minus 24% of the eligible capital.
b) The reduction in the economic value due to the adverse impact minus 24% of the economic value before the impact.
- General option: institutions should use the in-house methodologies they consider to be most suitable, which they should substantiate and use in managing this risk. In this case, institutions should also calculate their capital needs under the simplified option and adjust appropriately, if required by Section 3.4.2 of these guidelines, the capital needs for solvency purposes. The more the result given by the simplified option differs from that calculated with in-house methodology, the more exhaustive the reasons given to justify the latter should be. It is permissible for the measurement of capital needs for this risk to give a result of no capital need, but institutions must justify this outcome.
The capital report should set out the option used and the result obtained. The institutions using the general option should summarise the methodology used and its basis.
3.3.6 Assessment of capital needs for liquidity risk
Institutions may replace their estimate of the capital required to cover this risk by an analysis of their liquidity policy, liquidity control systems and contingency plans, giving evidence that they have adequate liquidity and do not need capital to cover this risk. Institutions unable to provide evidence of adequate liquidity should establish an action plan and allocate capital to cover this risk.
The capital report should include a summary of the liquidity policy and situation and state the capital allocated, if any, to cover this risk.
3.3.7 Assessment of capital needs for other risks
To assess capital needs for other risks, institutions should use one of the following options:
- Simplified option: instead of assessing the capital required to cover these risks, institutions may allocate capital equal to 5% of their total minimum capital requirements under Pillar 1.
- General option: institutions should use the in-house methodologies they consider to be most suitable, which they should substantiate and use in managing this risk. Institutions should report at least their reputational and business risks, including the procedures for estimating and monitoring them. They should also assess any other risk they consider to be material.
Institutions with significant exposures derived from their insurance business (through subsidiaries) should analyse them and allocate capital to cover this risk, not deducting from capital in this case the shareholdings in these subsidiaries. Alternatively they may deduct the shareholdings in insurance subsidiaries, indicating the solvency situation of these subsidiaries in accordance with insurance regulations, which must cover such risks sufficiently.
In addition, any material risks derived from future pension commitments or any other commitment of institutions should be assessed and covered adequately, if this has not already been done.
Institutions using this option for reputational or business risks may employ the simplified option for the rest, assigning a conservative coefficient instead of the general value of 5% under the simplified option.
Reputational risk should include, inter alia, the risk derived from all of a credit institution’s dealings with customers that could result in negative publicity concerning its practices and business relations and, consequently, a loss of confidence in its moral integrity.
Business risk should include the risk of hypothetical (internal or external) adverse events that negatively affect an institution’s ability to achieve its objectives and consequently have a negative effect on earnings (profit and loss account) and, through the latter, on solvency.
The capital report should set out the option used and the result obtained, if any. The institutions using the general option should summarise the methodologies used and their basis.
3.4 Aggregation of capital needs and reconciliation adjustments
3.4.1 Aggregation of capital needs for the various risks
The aforementioned individual estimate of capital needs for the various risks should be used in this section to determine the total necessary capital. There are both simplified and general aggregation options for aggregating capital needs.
- Simplified aggregation option: institutions should calculate their total capital needs by simple summation of the capital required to cover each of their risks separately, as per the result of the individual measurements in Section 3 above. This option should be used by the institutions that use standardised approaches under Pillar 1.
- General aggregation option: the institutions that use advanced approaches under Pillar 1 to measure some of their risks (credit, market and operational) and also use quantitative models for overall management of all their risks may use in these models, aggregation formulas enabling the benefits of inter-risk diversification to be included. These models should be used in the institution’s overall risk management and must be capable of allocating capital to the various business units on the basis of their different risk profiles. Institutions that use the general aggregation option should also calculate their capital needs by simple summation. The greater the difference between the result of simple summation and that calculated using an in-house methodology, the more exhaustive the rationale for the latter should be. .
The capital report should set out the option used, the result obtained and, moreover:
- The institutions using the simplified option should limit themselves to completing the numerical data in the summary table in Annex 1.
- The institutions using the general aggregation option should also summarise the methodology used and its basis, making reference to such internal documents as they consider necessary.
3.4.2 Adjustments made to reconcile the management and solvency approaches
As mentioned in Section 2.2, the ICAAP should be based on the risk analysis carried out by institutions for risk management purposes. Hence for some risks it may be necessary to make adjustments to reconcile the capital figures used in the management of certain risks to those used from a solvency standpoint.
The purpose of these adjustments is to offset the greater capital needs of the management approach with funds (e.g. unrealised capital gains or economic value) not counted for solvency purposes, but that the management model does consider and seeks to protect. Described below, by way of examples, are two situations in which such adjustments may be necessary:
- Quoted shares carried at cost in the long-term investment portfolio and on which there are unrealised gains. In this case it may be suitable to use for management purposes a quantitative model (e.g. VaR) applied at the current market value of the shares. This approach aims to preserve the value of the shares (including the unrealised gains) and would therefore foreseeably result in a capital need figure above that calculated under Pillar 1 if the institution is using a default approach (PD/LGD) in Pillar 1 based on book value. In this situation and for the purpose of ICAAP solvency analysis, institutions may prudently offset the higher capital needs of the management approach against a part of the gains not considered to be capital under Pillar 1.
- Exposure to interest rate in the banking book. In institutions that use in-house models (general option), the capital needs figure under a management approach may be high if the institution seeks to preserve the economic value of its balance sheet. However, the economic value will, in turn, if sufficiently high, protect the institution’s solvency from an adverse impact of interest rates, although the institution’s net interest margin may deteriorate. In this situation, and for the purpose of ICAAP solvency analysis, institutions may offset, again prudently, the capital needs under their own model against a part of the economic value of the balance sheet.
For these purposes, institutions should assess consistently and prudently under the ICAAP the risks and the available capital associated with them. In this connection, as an example relating to quoted equity securities, an approach to assessing capital needs based on default and consequent loss of a considerable part of the value of the investment (PD/LGD approach) should not imply that the related unrealised gains are eligible as capital available to cover this or other risks.
3.5 Capital planning[7]
In planning their future capital needs derived from compliance with their future capital requirements under Pillar 1, institutions should include the assessment of all additional risk exposures carried out in the ICAAP. For this purpose, every year they should estimate the capital sources and allocations within their planning horizon, which they should define for this purpose and which should not be less than three years.
In order to do so, they should make projections, considering the institution's strategic plan, of the capitalised profit, dividends, share issues, subordinated capital issues, and capital charges derived from expected business growth, from changes in the Pillar 1 risk profile, from other risks assessed in the ICAAP, from one-off transactions, etc.
In this section, stress tests should be conducted to identify those events or changes in the market conditions in which institutions operate that may adversely affect their future solvency.
Each year institutions should carry out and reflect in their capital report a macro stress test that considers a scenario of general deterioration derived from a significant fall in economic activity (recession). This scenario should reflect sufficiently adverse behaviour of a combination of at least GDP, interest rates, the unemployment rate and housing prices.
Institutions should also conduct other stress tests if relevant to them. As examples, the following may be mentioned:
- Specific deterioration of the economic sectors in which an institution’s activity is concentrated.
- Situations of special tension and volatility in the money markets and those for other financial products.
- Scenarios of significant stock market falls.
- Scenarios of serious operating losses.
- Scenarios of liquidity crisis.
- Scenarios of errors in the valuation of complex financial products.
These stress scenarios must be sufficiently intense and encompass situations that have occurred in an institution’s markets over a sufficiently long period (for example, situations in the last 20-30 years) and may consider active management strategies to mitigate its effects.
The institutions using advanced approaches under Pillar 1 (IRB, VaR, AMA) should specifically conduct stress tests to assess how adverse events may affect their future capital requirements under Pillar 1 derived from the use of the related advanced approaches. Specifically, institutions using IRB models for credit risk should estimate the changes in their Pillar 1 capital requirements derived from ratings variations during the business cycle (migrations). These changes in Pillar 1 capital requirements should be considered in capital planning.
The additional capital needs derived from the different stress tests, both for Pillar 1 risks and for other material risks identified in the ICAAP, should be estimated and, where applicable, possible alternative capital elements identified to cover them. For these purposes, such elements may include a prudent assessment of unrealised gains and other items of a similar nature, as well as a prudent estimate of additional capital of other types (core capital, Tier 1 capital and Tier 2 capital) that the institution could generate if needed. When quantifying these alternative capital elements, it should be kept in mind that they will probably be used in crisis situations.
The contingency plans in place for use in case of unforeseen divergences and events should be explained in the capital planning.
The presentation of the stress tests should not consider any alternative sources of capital or active management strategies undertaken to mitigate the impact, i.e. the outcome should be presented gross of mitigation. Where appropriate the impact of the mitigation produced by alternative sources of capital or any other action should be explained separately in this section.
This section of the capital report should set out the following:
- The period covered by the planning, which must not be under three years.
- Analysis of deviations in the period with respect to the planning prepared in the prior period.
- Summary of the planning methodology used and of its results.
- Summary of the stress tests conducted and of their results.
- Summary and quantification of any alternative capital sources.
The capital report should include the estimates of the macroeconomic variables used as inputs in the capital plan and in the macro stress test. It should also include those elements of the strategic plan and accounting planning that are considered to be significant in the projections made.
This section should reflect, for the various stress tests included in the capital planning and the macro stress test, the estimated amount of the main balance sheet items (including loans and receivables in the public and private sectors, deposits from the private sector, loans in arrears and loan loss provisions), a representative disaggregation of risk-weighted assets, net interest income, gross income, net operating income and profit or loss before tax. Significant direct adjustments to equity expected in the period covered by the planning should also be indicated, as well as planned issues or retirements of equity capital, regardless of the nature of the instruments involved (core capital, Tier 1 capital or Tier 2 capital).
These stress tests should take into account the EBA document “Guidelines on Stress Testing (GL32). EBA recommendations should be followed when carrying out of the macro stress test unless the institution considers them inappropriate. The estimates of macroeconomic magnitudes provided by the European Central Bank (ECB) should also be taken into account.
3.6 Programme of future measures
Based on the assessments set out in Section 3.2 and the estimates included in Sections 3.3 to 3.5, the main deficiencies and weaknesses found should be summarised and, if significant, an action plan drawn up to remedy them. This action plan may include the following measures, among others:
- Modification of the institution’s risk profile: reduction of a certain activity or activities, application of new risk mitigation techniques, etc.
- Improvements in governance and internal organisation; improvements in risk management and internal control.
- Modification of the own funds target, stating the related adaptation period, if appropriate.
This section should also set out the future changes in risk and capital management that the institution intends to undertake, such as changes in the general risk policy, improvements in the management and control tools for a particular risk, changes in Pillar 1 approaches, etc. In any event, all matters relating to plans for future improvement should be included only in this section, although cross-references to them can be made in other sections.
3.7 Other matters
Other matters that institutions consider it necessary or useful to include in the report and have not been addressed in any other section should be set out here.
| [6] |
Wording as in the Banco de España Executive Commission resolution of 18.03.09
|
| [7] |
Wording as in the Banco de España Executive Commission resolution of 26.01.11
|
| [8] |
Wording as in the Banco de España Executive Commission resolution of 26.10.12.
|
| |
|